Products designed for industrial applications.
General terms and conditions for sale are available on
www.camozzi.com.3
Series MC soft start valves
TREATMENT >
CATALOGUE
>
Release 8.7
/2.35.03
3
TREATMENT
Pressurisation times as to the n° of turns of the regulation screw,
with downstream volume of 5 litres. A = 5 turns - B = 4 turns - C =
3 turns - D = 2 turns - E = 1 turn. “K” = n° of turns of the regula-
tion screw required to obtain the required pressurisation time with
an inlet pressure of 6 bar. Variations of the inlet pressure can
cause deviations of the pressure time by ± 20%. K = t/V where: V
= volume of the downstream system in litres; t = desired pressur-
ing time in seconds.
Pressurisation times as to the n° of turns of the regulation screw,
with downstream volume of 5 litres. A = 9 turns - B = 7 turns - C =
5 turns - D = 3 turns - E = 1 turn. “K” = n° of turns of the regula-
tion screw required to obtain the required pressurisation time with
an inlet pressure of 6 bar. Variations of the inlet pressure can
cause deviations of the pressure time by ± 20%. K = t/V where: V
= volume of the downstream system in litres; t = desired pressur-
ing time in seconds.
DIAGRAMS FOR PRESSURISATION TIMES
Example: MC104-AV
V = 5 litres
t = 16 seconds
K = 16/5 = 3,2
g = number of turns
Using in the graph this value K, the number of turns of the regula-
tion screw will be approx. 1,8.
Example: MC238-AV - MC202-AV
V = 5 litres
t = 16 seconds
K = 16/5 = 3,2
g = number of turns
Using in the graph this value K, the number of turns of the regula-
tion screw will be approx. 1,8.
VARIATION IN PRESSURISATION - Example